(1) The State Load Despatch Centre in a State may give such directions and exercise such supervision and control as may be required for ensuring the integrated grid operations and for achieving the maximum economy and efficiency in the operation of power system in that State.
(2) Every licensee, generating company, generating station, sub-station and any other person connected with the operation of the power system shall comply with the directions issued by the State Load Despatch Centre under sub-section (1).
Legal Commentary & Landmark Judgments: Section 33
Section 33 of the Electricity Act, 2003 establishes the legally binding authority of SLDC directions over all intra-State licensees, generating stations, and sub-station operators, providing penal liabilities for disobedience and a dispute resolution process before the SERC.
In intra-State grid disputes, advise clients never to defy SLDC real-time dispatch instructions; always log formal technical objections electronically, comply with the directive, and immediately initiate dispute adjudication before the SERC under Section 33(4).