Section 67: Effect of neglect of promisee to afford promisor reasonable facilities for performance
Indian Contract Act • Official Statutory Text & Practice Guide
Statutory Regulation
Legal Standard
Competent Court / Tribunal
Act 1872
Indian Contract Act • Official Statutory Text & Practice Guide
Legal Commentary & Landmark Judgments: Section 67
Section 67 of the Indian Contract Act, 1872 codifies the statutory defense of promisee non-cooperation, providing that if any promisee neglects or refuses to afford the promisor reasonable facilities for the performance of his promise, the promisor is excused by such neglect or refusal as to any non-performance caused thereby.
In EPC, turn-key, and construction arbitrations, compile a contemporaneous delay matrix tracking employer defaults (delayed site handover, pending drawings, utility delays). Plead Section 67 as a complete statutory defense to counter liquidated damages, milestone deductions, or contract termination invoked by the employer.