RERA Escrow Accounts & Cheque Dishonour: Personal Liability of Promoter Directors
Executive Legal Brief
- Section 4(2)(l)(D) of RERA mandates real estate promoters to deposit 70% of customer collections into a designated project escrow bank account.
- Funds from this RERA escrow account can only be withdrawn for land purchase and construction costs, certified by an architect, engineer, and chartered accountant.
- When contractor or vendor cheques drawn on a RERA escrow account bounce, designated project directors cannot claim immunity behind general corporate shields.
- Promoters who unlawfully divert escrow funds face concurrent penal prosecution under Section 138 NI Act and Section 59/60 of the RERA Act.
Key Statutory Provisions & Regulatory Framework
| Statutory Provision / Doctrine | Legal Operation & Judicial Impact |
|---|---|
| Section 4(2)(l)(D) RERA, 2016 | Mandates 70% project escrow bank account strictly ring-fenced for construction and land costs. |
| Section 138 NI Act, 1881 | Criminal liability of developer company and signatory authority for dishonour of vendor/contractor cheques. |
| Section 141 NI Act, 1881 | Vicarious liability of designated promoter directors and authorized signatories managing the escrow account. |
| Section 60 RERA, 2016 | Penal sanctions against real estate promoters for providing false information or violating RERA directions. |
1. The Statutory Mandate of RERA 70% Project Escrow Accounts
Prior to the enactment of the Real Estate (Regulation and Development) Act, 2016 (RERA), real estate developers routinely diverted buyer funds from one project to purchase new land parcels, starving ongoing construction of liquidity. To curb this abuse, Parliament enacted Section 4(2)(l)(D) of RERA.
Under this provision, the promoter must deposit seventy percent (70%) of the amounts realized for the real estate project from allottees into a separate bank account maintained in a scheduled bank to cover the cost of construction and land cost, to be used exclusively for that purpose.
2. Dishonour of Contractor Cheques Drawn on RERA Escrow Accounts
Civil contractors, raw material suppliers, architects, and engineering consultants working on RERA-registered projects are paid through cheques drawn directly on the designated project escrow account. When these cheques bounce due to insufficient funds, it signals illegal siphoning or uncertified withdrawals by promoters.
In Section 138 complaints filed by unpaid contractors:
- Direct Corporate Liability: The builder company is prosecuted as the drawer of the instrument.
- Personal Vicarious Liability under Section 141: The authorized signatory director who signed the cheque and the designated project directors listed in the RERA registration certificate are personally liable.
3. Defenses Available to Non-Executive and Independent Directors
Under RERA compliance filings, companies appoint technical directors or independent professionals who have no control over bank mandates or escrow funds. Under the doctrine of Sunita Palita v. Panchami Stone Quarry (2022) 10 SCC 152, independent and non-executive directors who are not signatories to the escrow bank account are exempt from Section 141 vicarious liability, provided they place Form DIR-12 and RERA disclosures on record.
Disclaimer: This article is published strictly for academic and educational purposes under the Advocates Act, 1961. It does not constitute formal legal advice, solicitation, or advertisement under Rule 36 of the Bar Council of India Rules, nor does it create an advocate-client relationship. For case-specific legal counsel, readers should consult an independent advocate.
Frequently Asked Questions
Can a builder claim that RERA escrow rules prevent them from paying Section 138 compensation?
No. RERA escrow restrictions mandate using funds for construction and vendor costs. Cheques issued to contractors are legitimate project expenses and must be honoured.
Can a contractor file a complaint in both RERA and Section 138 court?
Yes. A contractor can initiate criminal proceedings under Section 138 before the Judicial Magistrate while simultaneously reporting escrow diversion to the RERA Authority under Section 59/60.
Are all directors of a real estate firm liable for escrow cheque dishonour?
Only executive directors, managing directors, and authorized signatories involved in day-to-day project finance are liable under Section 141 NI Act.